Home Terminal Gebze is Expanding

The expansion of the Gebze terminal is on the agenda of YILPORT for some time. As further the necessary regulations and terminal development projects, YILPORT Gebze will have additional 10,000 square meters area after the completion of demolition and construction works. As per to the plan which is expected to be finished completely by the second quarter of 2018, the new area will be equipped with RTG blocks for container operations.

Another expansion is planned to be finished by the end of March 2018. As per to the plan, it will be completed in two phases. Additional 400 TEUs will be ready by the end of December in 2017. The last planned phase is also planned to be finished by the end of March 2018 and provide 720 TEUs. With this latest expansion, the total area of the new yard will reach up to 34,000 square meters.